[Dec-2021 Newly Released] C_TS422_2020 Exam Questions For You To Pass
SAP C_TS422_2020 Exam: Basic Questions With Answers
SAP S/4HANA Production Planning and Manufacturing Certification Exam Details:
| Exam Name | SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing |
| Duration | 180 mins |
| Exam Code | C_TS422_2020 |
| Passing Score | C_TS422_2020 - 56% C_TS422_1909 - 55% |
| Schedule Exam | SAP Training |
NEW QUESTION 30
When working with both cross-plant and plant-specific material statuses in the mater al master, which status has the highest priority?
- A. The cross-plant status
- B. The most restrictive status
- C. The plant-specific status
- D. The least restrictive status
Answer: B
NEW QUESTION 31
What data can you maintain in the sub items of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. Installation point
- B. Scrap percentage
- C. Quantity
- D. Item type
Answer: A,C
NEW QUESTION 32
A material has been set up as a phantomassembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material(BOM)?
- A. Change the item category of the phantom assembly in the BOM.
- B. Change the explosion type of the phantom assembly in the BOM.
- C. Change the phantom item indicator for the phantom assembly in the BOM.
- D. Change the special procurement key of the phantom assembly in the BOM.
Answer: B
NEW QUESTION 33
Which time elements can be reduced by a reductionstrategy? Note: There are 3 correct answers to this question.
- A. Wait time
- B. Goods receipt processing time
- C. Queue time
- D. Float after production
- E. Move time
Answer: C,D,E
NEW QUESTION 34
Which time elements are relevant for lead t me scheduling of a product on order? Note: There are 2 correct answers to this question.
- A. Planned delivery time
- B. Setup time
- C. Total replenishment lead time
- D. Float after production
Answer: A,D
NEW QUESTION 35
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.
- A. Change of the storage bin
- B. Creation of a purchasing contract
- C. Change of the material'sprocurement type
- D. Creation of a sales order
- E. Creation of dependent requirements
Answer: C,D,E
NEW QUESTION 36
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?
- A. Resource network
- B. Setup matrix
- C. Work center hierarchy
- D. Operation network
Answer: C
NEW QUESTION 37
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note:There are 2 correct answers to this question.
- A. Planned delivery time
- B. Operation duration
- C. Total replenishment lead time
- D. In-house production time
Answer: A,D
NEW QUESTION 38
What are the consequences if operation status Dispatched is set for a production order operation?
- A. You can reschedule the operation using finite Scheduling in a planning board.
- B. You can reschedule the operation using lead the scheduling.
- C. You can reschedule the order using lead time scheduling.
- D. You canreschedule the order using material requirements planning.
Answer: A
NEW QUESTION 39
What does a line hierarchy in repetitive manufacturing represent?
- A. A production line with an alternative sequence in the routing
- B. A production line with prioritized alternative work centers
- C. A production line with more than one work center
- D. A production line with a parallel sequence in the routing
Answer: C
NEW QUESTION 40
What are some uses for the low-level code assigned to each material? Note: There are 2correct answers to this question.
- A. It is used by ATP to determine the priority of alternative components.
- B. It is used in MRP to determine the sequence in which materials are planned.
- C. It is used by engineering to identify sub items in an engineering bill of material(BOM).
- D. It is used by product costing to determine how costs are rolled up.
Answer: B,D
NEW QUESTION 41
You have maintained the parameters for simple discontinuation the material master of a component. Which business process will be affected if the available stockis zero and the discontinuation date is in the past?
- A. Kanban
- B. Material requirements planning
- C. Production order release
- D. Back flushing
Answer: B
NEW QUESTION 42
For a production version to be valid and consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.
- A. Thedeletion flag must NOT be set for the bill of materials (BOM) or the routing.
- B. The lot size range must be within the lot-size range of the assigned routing.
- C. The assigned routing and bill of materials (BOM) must be valid in the entire validity period.
- D. The assigned routing must NOT have alternative sequences.
- E. The assigned routing must be a rate routing.
Answer: A,B,C
NEW QUESTION 43
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.
- A. The planning strategy is infinite.
- B. Alternative resources are fully occupied.
- C. The work center has several individual capacities.
- D. The Change Planning Direct on indicator is set.
Answer: A,C
NEW QUESTION 44
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?
- A. When multiple planned orders exists in one resource
- B. When alternate resourcesare used within one operation
- C. When multiple production versions are maintained for one product
- D. When multiple operations are maintained for one product
Answer: B
NEW QUESTION 45
Which actions does the system perform by default when you save aconfirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.
- A. Posting of production costs to the production cost collector
- B. Archiving of documents for assembly scrap
- C. Posting of goods receipt for the product
- D. Reduction of associated capacity requirements
- E. Material staging for next order in sequence
Answer: A,C,D
NEW QUESTION 46
You run MRP for a material that was planned using Demand-Driven Replenishment. Toward which buffer level does the MRP run create a replenishment proposal?
- A. Top of Red
- B. Top of Red Base
- C. Top of Yellow
- D. Top of Green
Answer: D
NEW QUESTION 47
What are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 3 correct answers to this question.
- A. Create object selection variant for transportation lane-related alerts.
- B. Create object selection variant for product-related alerts.
- C. Assign the alert profile to the overall profile.
- D. Create object selection variant for resource-related alerts
- E. Assign the overall profile to the authorization profile.
Answer: B,C,D
NEW QUESTION 48
When do you use variant bills of materials (BOMB)?
- A. When multiplematerial is have similar BOMB
- B. When a material has multiple BOMB
- C. When multiple material also have the same BOM
- D. When a material has a configurable BOM
Answer: C
NEW QUESTION 49
......